Brunel begins sinking exploratory shafts to examine the geology along the proposed route through Box Hill.
Brunel, Isambard Kingdom · Box HillBox Tunnel
The major Great Western Railway tunnel through Box Hill

Historical chronology
11 matching records from the updated 653-record Brunel dataset.
Work begins on Box Tunnel through Box Hill for the Great Western Railway.
Brunel, Isambard Kingdom · Box HillDifficult rock strata and heavy water ingress delay excavation, with less than half of the tunnel completed.
Brunel, Isambard Kingdom · Box HillThe railhead at Chippenham served as an interim endpoint pending the completion of the line through Box Tunnel.
Brunel, Isambard Kingdom · Chippenham GWRThe railway approaches toward Box Tunnel carried trains eastward from Bath on the completed main line.
Brunel, Isambard Kingdom · Bath AvonOpening the Box Tunnel completed the route through the hills east of Bath and connected the Avon valley to Chippenham.
Brunel, Isambard Kingdom · Bath AvonThe western entrance is finished with a more elaborate architectural treatment than the simpler eastern portal.
Brunel, Isambard Kingdom · Box HillBrunel pushes the main contractor to increase the Box Tunnel workforce from about twelve hundred to four thousand men.
Brunel, Isambard Kingdom · Box HillOpening the long Box Tunnel connected Chippenham by rail with Bath and the Bristol section beyond.
Brunel, Isambard Kingdom · Chippenham GWRThe opposing tunnel workings meet with an alignment error of less than two inches and construction is completed.
Brunel, Isambard Kingdom · Box HillBox Tunnel opens as the longest railway tunnel in the world at the time.
Brunel, Isambard Kingdom · Box Hill