Clifton Suspension Bridge

Brunel's celebrated bridge design across the Avon Gorge

Historic 1872 illustration of Clifton Suspension Bridge
Historic 1872 illustration of Clifton Suspension Bridge — Image: Wikimedia Commons source and licence

Historical chronology

43 matching records from the updated 653-record Brunel dataset.

1753 — Vick Bequeaths Funds For Avon Gorge Crossing

Person: Vick, William · Place: Bristol · Country: Great Britain

Bristol merchant William Vick leaves one thousand pounds in his will to finance a future crossing of the Avon Gorge, establishing the bequest from which the Clifton bridge project eventually develops.

1828 — Recovery

Person: Brunel, Isambard Kingdom · Place: Brighton · Country: Great Britain

While recovering from his tunnel injuries Brunel develops ideas for a suspension bridge across the Avon Gorge.

1829 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel submits designs to the competition for a suspension bridge across the Avon Gorge at Clifton.

1829 — Avon Gorge Bridge Design

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Enters the competition while still a young independent engineer.

1829 — First Clifton Bridge Competition

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Submits designs to the first Clifton Suspension Bridge competition.

1829 — Clifton Suspension Bridge Design Submitted

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Brunel entered the competition to build a suspension bridge spanning the gorge between Clifton and Leigh Woods.

1829 — Brunel Enters Four Clifton Designs

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Isambard Kingdom Brunel submits four distinct proposals to the initial competition for an Avon Gorge suspension bridge, challenging conventional assumptions about span length.

1829 — Telford Rejects Long Suspension Spans

Person: Telford, Thomas · Place: Bristol · Country: Great Britain

As a judge of the first bridge competition, Thomas Telford raises objections to proposed long suspension spans over the Avon Gorge and rejects the shortlisted schemes.

1830 — Second Clifton Suspension Bridge Competition

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Submits revised designs in the second competition for a bridge across the Avon Gorge.

1830 — Telford Competition Judgement Challenged

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel continues promoting his Avon Gorge design after Thomas Telford rejects the first competition entries and proposes his own bridge.

1830 — Clifton Bridge Design Reconsidered

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

A revised bridge competition considered competing proposals for crossing the Avon Gorge.

1830 — Gilbert Reviews Clifton Competition Finalists

Person: Gilbert, Davies · Place: Bristol · Country: Great Britain

Davies Gilbert serves among the judges who consider the finalists in the renewed Clifton bridge competition and assess the engineering feasibility of the rival schemes.

1830 — Rendel Submits Competing Bridge Scheme

Person: Rendel, James Meadows · Place: Bristol · Country: Great Britain

James Meadows Rendel participates in the renewed competition for the Clifton crossing, joining other established engineers in proposing a bridge across the gorge.

1830 — Seaward Evaluates Clifton Bridge Designs

Person: Seaward, John · Place: Bristol · Country: Great Britain

Civil engineer John Seaward judges competing proposals for the Clifton Suspension Bridge and participates in the assessment that initially places Brunel behind another entrant.

1830 — Brown Competes For Clifton Crossing

Person: Brown, Samuel · Place: Bristol · Country: Great Britain

Engineer Samuel Brown enters the renewed Clifton bridge design competition, offering a rival suspension bridge proposal to the one developed by Isambard Kingdom Brunel.

1830 — Hawkes Design Initially Preferred By Judges

Person: Hawkes, William · Place: Bristol · Country: Great Britain

The judges initially prefer a design by William Hawkes of the Eagle Foundry in the second Clifton competition before Brunel revises his competing proposal.

1830 — Clifton Suspension Bridge Competition

Person: Telford, Thomas · Place: Bristol · Country: Great Britain

Acts as judge during the Clifton Suspension Bridge design competition.

1831 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel secures acceptance of his revised suspension bridge design and becomes project engineer.

1831 — Construction

Person: Brunel, Isambard Kingdom · Place: Clifton · Country: Great Britain

Work begins on the Clifton Suspension Bridge, one of Brunel's earliest major independent projects.

1831 — Clifton Bridge Cost Estimate Prepared

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel estimates the suspension bridge project at about fifty-seven thousand pounds, including architectural treatment of the towers.

1831 — Clifton Main Span Fixed at 214 Metres

Person: Brunel, Isambard Kingdom · Place: Avon Gorge · Country: Great Britain

Brunel's accepted scheme uses a main suspension span of about 214 metres across the Avon Gorge.

1831 — Revised Clifton Scheme Accepted

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Brunel's revised suspension bridge proposal was selected for the planned crossing of the Avon Gorge.

1831 — Clifton Gorge Bridge Works Begin

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Initial work commenced on the bridge project but civil disturbances in Bristol disrupted early progress.

1831 — Bristol Riots Interrupt Bridge Finance

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

The unrest in Bristol undermined investor confidence and contributed to suspension of early bridge work.

1831 — Brunel Estimates Fifty Seven Thousand Pounds

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel estimates the Clifton Suspension Bridge project at approximately fifty seven thousand pounds, including elaborate treatment of the towers and suspension works.

1831 — East Gorge Foundation Stone Laid

Person: Brunel, Isambard Kingdom · Place: Clifton · Country: Great Britain

Construction of Brunel's proposed suspension bridge formally begins with the laying of a foundation stone on the Clifton side of the Avon Gorge in June 1831.

1831 — Egyptian Style Incorporated Into Clifton Design

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel develops Egyptian inspired architectural features for the planned Clifton bridge towers, integrating monumental appearance with the proposed iron suspension structure.

1831 March 16 — Clifton Bridge Engineer Appointed

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel is appointed engineer for the Clifton Suspension Bridge after his revised design is selected.

1831 June 20 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

A ceremony marks the start of construction and work begins on the Clifton side of the gorge.

1831 October — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Construction is halted after the Bristol riots damage confidence and stop subscriptions to the bridge company.

1836 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Construction resumes after renewed commercial confidence brings further investment to the project.

1836 — Leigh Woods Foundation Stone Laid

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Construction resumed with a ceremony marking the foundation of the western bridge abutment.

1836 — Leigh Woods Foundation Ceremony Held

Person: Brunel, Isambard Kingdom · Place: Leigh Woods · Country: Great Britain

On 27 August 1836, the foundation stone of the Leigh Woods abutment is laid as bridge construction resumes after years of financial and political interruption.

1836 August 27 — Leigh Woods Abutment Foundation Laid

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Construction restarts with the foundation stone for the Leigh Woods abutment laid on the western side of the gorge.

1837 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

The main contractors fail financially, but the bridge towers are raised in unfinished stone.

1837 — Clifton West Abutment Work Progresses

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Construction teams developed the masonry support at Leigh Woods for the planned suspended bridge deck.

1837 — Western Abutment Contractor Fails

Person: Brunel, Isambard Kingdom · Place: Leigh Woods · Country: Great Britain

The company undertaking work on the Leigh Woods abutment encounters financial failure, disrupting renewed construction on Brunel's Clifton suspension bridge.

1838 — Clifton Eastern Tower Masonry Advances

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Contractors continued the Clifton side tower and its supporting masonry above the Avon Gorge.

1839 — Bridge Anchor Tunnels Constructed

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Engineers excavated and built underground anchorage structures to resist the future suspension chain loads.

1839 — Hungerford Suspension Bridge Layout Planned

Person: Brunel, Isambard Kingdom · Place: Hungerford · Country: Great Britain

Design work considered a high central suspension span supported by masonry towers and anchored iron chains.

1840 — Clifton Chain Contract Awarded

Person: Brunel, Isambard Kingdom · Place: Hayle · Country: Great Britain

The Copperhouse Foundry at Hayle receives the contract to manufacture suspension chains for Brunel's Clifton bridge.

1840 — Clifton Bridge Chain Contract Awarded

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

The bridge project arranged manufacture of its suspension chains at the Copperhouse Foundry in Cornwall.

1840 — Hungerford Suspension Chain Design Prepared

Person: Brunel, Isambard Kingdom · Place: Hungerford · Country: Great Britain

Brunel adopted wrought iron suspension chains to support the bridge deck across the Thames.

1840 — Hungerford Bridge Chain Manufacture Commences

Person: Brunel, Isambard Kingdom · Place: Hungerford · Country: Great Britain

Chain manufacture at the Copperhouse Foundry supported the large suspension bridge projects undertaken by Brunel.

1840 — Copperhouse Foundry Receives Chain Contract

Person: Brunel, Isambard Kingdom · Place: Hayle · Country: Great Britain

The Clifton bridge undertaking contracts with Copperhouse Foundry in Hayle to produce suspension chains, although the project's financial difficulties later prevent their intended installation.

1840 — Leigh Woods Abutment Construction Advances

Person: Brunel, Isambard Kingdom · Place: Leigh Woods · Country: Great Britain

The Leigh Woods masonry abutment reaches an advanced state by 1840, forming a substantial foundation for the suspension structure planned across the gorge.

1841 — Clifton Suspension Tower Building Continues

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Stone towers rose above the gorge while work on abutments and chain anchorage structures proceeded.

1842 — Clifton Anchor Tunnels Completed

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

The bridge towers, abutments and four anchor tunnels are substantially completed before the project again runs short of money.

1842 — Clifton Tower And Anchorage Works Finished

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

The towers abutments and principal anchor tunnels had been substantially completed by 1842.

1842 — Hungerford Stone Towers Under Construction

Person: Brunel, Isambard Kingdom · Place: Hungerford · Country: Great Britain

Masonry towers were built to support the suspension chains and the elevated pedestrian deck.

1842 — Four Chain Anchor Tunnels Completed

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Work on the original Clifton bridge scheme produces four anchorage tunnels by 1842, alongside the towers and abutments intended to secure the proposed iron chains.

1842 — Original Piers And Abutments Stand Ready

Person: Brunel, Isambard Kingdom · Place: Avon Gorge · Country: Great Britain

The principal stone piers and abutments of Brunel's original design are substantially complete by 1842, despite the continued absence of a suspended roadway.

1843 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Funds are exhausted and construction stops before the chains and roadway can be completed.

1843 — Clifton Ironwork Funding Shortfall

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Construction stalls because the bridge company lacks the funds needed to complete the chains and roadway.

1843 — Clifton Bridge Funds Run Short

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Construction slowed dramatically when available capital proved insufficient to complete the deck and ironwork.

1843 — Hungerford Bridge Suspension Chains Assembled

Person: Brunel, Isambard Kingdom · Place: Hungerford · Country: Great Britain

Workers installed or prepared the massive iron links required to suspend the bridge across the river.

1843 — Remaining Ironwork Needs Additional Finance

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

With the masonry largely finished, the Clifton bridge project still requires roughly thirty thousand pounds for remaining ironwork, a shortfall that prevents completion of the crossing.

1845 — Hungerford Bridge Completed

Person: Brunel, Isambard Kingdom · Place: London · Country: Great Britain

Its chains are later reused to complete the Clifton Suspension Bridge.

1845 — Hungerford Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: London · Country: Great Britain

Completes the Hungerford Suspension Bridge across the Thames.

1845 — Clifton Bridge Remains Unfinished

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

The bridge's standing towers showed the project's progress but the span still lacked its suspended roadway.

1851 — Clifton Chains Diverted from Original Project

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Material intended for the unfinished Clifton bridge is disposed of after the project loses its remaining construction funds.

1851 — Clifton Materials Ordered Sold

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Brunel is ordered to suspend the unfinished bridge works and sell materials and plant to satisfy creditors.

1851 — Clifton Construction Suspension Ordered

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Financial problems forced the project's managers to halt work and seek ways to settle outstanding liabilities.

1851 — Brunel Ordered To Sell Bridge Materials

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Creditors direct Brunel to halt remaining Clifton bridge work and dispose of materials and plant in October 1851 as the undertaking struggles with its unpaid obligations.

1853 — Clifton Bridge Plant Sold

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Project materials and equipment were sold as the original construction effort came to an end.

1853 — Clifton Bridge Original Project Abandoned

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

The first construction programme stopped without completion of the bridge across the gorge.

1853 — Unused Clifton Ironwork Redirected To Saltash

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Iron chains originally acquired for the unfinished Clifton project are sold and subsequently used in Brunel's Royal Albert Bridge at Saltash after funding for Clifton collapses.

1853 July — Clifton Bridge Works Abandoned

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Construction of the Clifton Suspension Bridge is completely abandoned.

1853 July — Clifton Construction Suspended

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

The unfinished project remains dormant when its statutory time limit expires.

1859 — Brunel Dies Before Clifton Completion

Person: Brunel, Isambard Kingdom · Place: Clifton Bridge · Country: Great Britain

Brunel died before the suspension bridge designed under his direction could carry passengers across the Avon Gorge.

1859 — Royal Albert Bowstring Tubular Principle Completed

Person: Brunel, Isambard Kingdom · Place: Saltash · Country: Great Britain

Brunel combines tubular compression arches with suspension chains to create the bridge's distinctive bowstring structural system.

1859 — Hawkshaw Supports Brunel Memorial Completion

Person: Hawkshaw, John · Place: Bristol · Country: Great Britain

Following Brunel's death, John Hawkshaw joins engineering colleagues who promote completion of the unfinished Clifton crossing as a lasting tribute to its designer.

1859 — Barlow Backs Bridge Memorial Campaign

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

William Henry Barlow helps revive interest in finishing the Clifton Suspension Bridge as a memorial to Brunel after the engineer dies in September 1859.

1860 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Chains from Brunel's dismantled Hungerford Suspension Bridge are purchased for use in completing the Clifton bridge.

1861 — Claxton Promotes Bridge Completion Legislation

Person: Claxton, Christopher · Place: Bristol · Country: Great Britain

Brunel supporter Christopher Claxton works to obtain parliamentary authority and financial arrangements needed to revive the Clifton Suspension Bridge undertaking.

1861 — Bridge Company Established For Completion

Person: Hawkshaw, John · Place: Bristol · Country: Great Britain

John Hawkshaw helps establish the organisation charged with finishing the abandoned Clifton Suspension Bridge and raising the resources required for renewed building.

1862 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

Construction restarts under a revised design by William Henry Barlow and John Hawkshaw.

1862 — Hawkshaw Specifies Triple Suspension Chains

Person: Hawkshaw, John · Place: Bristol · Country: Great Britain

John Hawkshaw's revised completion design provides three chains on either side of the bridge in place of the two chain arrangement in Brunel's earlier scheme.

1862 — Egyptian Tower Cladding Removed From Plans

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

The revised Clifton bridge design associated with Barlow omits Brunel's proposed Egyptian inspired iron tower cladding, leaving the monumental masonry visible.

1862 — Clifton Bridge Restarted

Person: Hawkshaw, John · Place: Bristol · Country: Great Britain

Hawkshaw helps restart work on the Clifton Suspension Bridge.

1863 — Chain Transport Traveller Runs Across Gorge

Person: Hawkshaw, John · Place: Avon Gorge · Country: Great Britain

The Clifton construction team uses a wheeled travelling apparatus running along temporary cables to move heavy suspension links into place above the river.

1863 — Nine Temporary Gorge Cables Installed

Person: Hawkshaw, John · Place: Avon Gorge · Country: Great Britain

During the summer of 1863 the bridge builders stretch nine substantial cables between the towers to support working platforms, transport equipment and chain installation.

1863 — Temporary Plank Platform Suspended Above Avon

Person: Barlow, William Henry · Place: Avon Gorge · Country: Great Britain

Workers suspend a narrow planked platform over the Avon Gorge from temporary cables, allowing them to assemble the chains that will ultimately carry the roadway.

1864 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

The completed structure is tested by placing about five hundred tons of stone across the bridge deck.

1864 — Manby Conducts Official Structural Inspection

Person: Manby, Charles · Place: Bristol · Country: Great Britain

On 7 November 1864 Sir Charles Manby examines the Clifton bridge for the government and reports favourably on its strength and workmanship.

1864 — Bridge Illuminated With Magnesium Flares

Person: Hawkshaw, John · Place: Bristol · Country: Great Britain

The Clifton bridge is illuminated for its December 1864 inauguration with contemporary lighting techniques including limelight and magnesium flares, although strong wind disrupts the display.

1864 — British Association Delegates Inspect Crossing

Person: Hawkshaw, John · Place: Bristol · Country: Great Britain

On 22 September 1864 John Hawkshaw helps show the nearly completed Clifton bridge to visiting members of the British Association for the Advancement of Science.

1864 — Quarried Stone Spread For Loading Test

Person: Hawkshaw, John · Place: Bristol · Country: Great Britain

In early November 1864 workers distribute stone across the Clifton bridge roadway, preparing the newly constructed span for a substantial proof load test.

1864 — Bridge Opening Date Confirmed By Directors

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

At a meeting on 3 November 1864 the Clifton bridge directors determine that the formal opening will take place on 8 December after earlier dates prove impractical.

1864 — Clifton Approach Road Prepared For Traffic

Person: Barlow, William Henry · Place: Clifton · Country: Great Britain

The completion works include cutting and finishing an approach road on the Clifton side, linking the new suspension bridge with the surrounding road network.

1864 — Clifton Span Passes Five Hundred Ton Test

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

Engineers test the completed Clifton suspension structure under approximately five hundred tons of stone and find its resulting deflection within acceptable limits.

1864 — Final Cross Girder Fixed Into Bridge

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

On 2 July 1864 the last main cross girder is installed, completing the structural framework on which the Clifton bridge roadway is subsequently laid.

1864 — Hungerford Ironwork Serves Clifton Opening

Person: Barlow, William Henry · Place: Hungerford · Country: Great Britain

The completed Clifton Suspension Bridge used salvaged chains from Brunel's former London crossing.

1864 — Last Suspension Chain Link Secured

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

On 8 May 1864 workers secure the final link among approximately four thousand two hundred suspension links, completing the bridge's principal supporting chains.

1864 — Opening Procession Brings Thousands Into Bristol

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

On 8 December 1864 the inauguration of the Clifton bridge draws a vast crowd to Bristol as military units and local trades process through the city.

1864 December 8 — Clifton Suspension Bridge

Person: Brunel, Isambard Kingdom · Place: Bristol · Country: Great Britain

The Clifton Suspension Bridge opens to the public as a memorial to Brunel five years after his death.

1864 December 8 — Clifton Bridge Opened

Person: Barlow, William Henry · Place: Bristol · Country: Great Britain

The Clifton Suspension Bridge opens to the public.

1908 — Royal Visit Marked By Bridge Lanterns

Person: VII, Edward · Place: Bristol · Country: Great Britain

The chains of the Clifton Suspension Bridge are decorated with coloured lanterns to commemorate the visit of King Edward VII to Bristol in 1908.

1911 — Coronation Illuminations Adorn Suspension Chains

Person: V, George · Place: Bristol · Country: Great Britain

Clifton Suspension Bridge is illuminated to celebrate the 1911 coronation of George V and Queen Mary, continuing a tradition of public decorative lighting.

1925 — King Visit Commemorated With Illuminations

Person: V, George · Place: Bristol · Country: Great Britain

The Clifton bridge is specially illuminated during the 1925 royal visit of King George V to Bristol, using lighting to mark the occasion.

1930 — Clifton Displays French Week Electric Lights

Person: Bristol Corporation · Place: Bristol · Country: Great Britain

During Bristol French Week in 1930, electric lights in French national colours illuminate the suspension bridge, reflecting its developing role in civic festivities.

1935 — Silver Jubilee Doubles Bridge Lighting Bulbs

Person: V, George · Place: Bristol · Country: Great Britain

Clifton bridge illuminations use approximately three thousand bulbs for the 1935 Silver Jubilee celebrations of King George V, expanding earlier electric displays.

1951 — Festival Of Britain Lighting Installed

Person: Clifton Suspension Bridge Trust · Place: Bristol · Country: Great Britain

For the 1951 Festival of Britain, the Clifton bridge is illuminated with thousands of bulbs, making the nineteenth century landmark part of a national celebration.

1953 — Coronation Lighting Spans Clifton Bridge

Person: II, Elizabeth · Place: Bristol · Country: Great Britain

The bridge receives extensive decorative lighting for the 1953 coronation of Elizabeth II, with illuminated chains and structures contributing to local celebrations.

1959 — Atkinson Photographs Brunel Centenary Lights

Person: Atkinson, Jane · Place: Bristol · Country: Great Britain

As a child, Jane Atkinson photographs the illuminated Clifton bridge in 1959 during events marking one hundred years since Brunel's death.

1964 — Centenary Illumination Marks Bridge Opening

Person: Clifton Suspension Bridge Trust · Place: Bristol · Country: Great Britain

The Clifton Suspension Bridge is lit with thousands of lamps in 1964 to celebrate the centenary of its original public opening.

2002 — Hungerford Chain Heritage Documented

Person: Clifton Suspension Bridge Trust · Place: Hungerford · Country: Great Britain

Conservation work on Clifton's suspension structure preserved evidence of iron links originally made for Hungerford Bridge.

2002 — Leigh Woods Abutment Chambers Identified

Person: Clifton Suspension Bridge Trust · Place: Clifton Bridge · Country: Great Britain

An engineering inspection revealed internal vaulted chambers inside the apparently solid Leigh Woods masonry abutment.

2002 — Leigh Woods Vault Interiors Surveyed

Person: Clifton Suspension Bridge Trust · Place: Leigh Woods · Country: Great Britain

An inspection at the Leigh Woods end of the Clifton Suspension Bridge identifies hollow vaulted chambers inside the masonry abutment previously thought to be solid.

2006 — Efficient LED Bridge Illumination Completed

Person: McArthur, Dayrell · Place: Bristol · Country: Great Britain

A modern LED lighting installation is completed on the Clifton Suspension Bridge in 2005 and 2006, reducing energy demand and avoiding excessive light pollution.

2014 — Clifton Bridge Anniversary Celebrated

Person: Clifton Suspension Bridge Trust · Place: Clifton Bridge · Country: Great Britain

The bridge marked 150 years since its opening as a lasting landmark of nineteenth century engineering.

2014 — Hungerford Chain Reuse Celebrated

Person: Clifton Suspension Bridge Trust · Place: Hungerford · Country: Great Britain

Interpretations of Clifton Bridge's history highlighted the recycled nineteenth century suspension chains from London.

2015 — Atkinson Recreates Historic Bridge Photograph

Person: Atkinson, Jane · Place: Bristol · Country: Great Britain

Jane Atkinson returns with the same photographic equipment she used in 1959 to recreate her childhood photograph of the illuminated Clifton bridge.

Search all Brunel chronology records