25–26 April 1986 · Unit 4

Chernobyl 25–26 April 1986: Hour-by-Hour Accident Timeline

A detailed reconstruction of the final day before the Chernobyl disaster and the accident itself, from the start of the planned shutdown through the turbine rundown test, reactor destruction, firefighting and first government response.

Chernobyl Reactor 4 after the 1986 accident
The chronology distinguishes exact logged times from broader response periods.
How to read this timeline. Exact clock times are used only where plant logs, instrument records or established technical chronologies support them. After the explosion, some actions are known only to the nearest part of the day, so this page uses “morning”, “afternoon” or approximate times rather than inventing precision.
Looking for the wider history? Open the full Chernobyl historical timeline for reactor design, construction, investigations, the original Shelter and New Safe Confinement.

The day before the explosion

Unit 4 is being shut down for planned maintenance. The turbine rundown experiment is intended to test whether a coasting turbine can temporarily power cooling pumps after loss of external electrical supply and before diesel generators take over.

01:06
Shutdown begins

The scheduled shutdown of Unit 4 starts and reactor power begins to fall gradually.

03:47
Power reduction pauses

The reduction stops at about 1,600 MW thermal.

14:00
ECCS isolated; grid delay begins

The emergency core cooling system is isolated as specified by the test programme. The Kyiv grid controller asks the plant to keep supplying power, so the test is delayed.

23:10
Power reduction resumes

The grid controller permits the shutdown to continue after the long delay.

24:00
Shift change

The operating shift changes while Unit 4 is still being prepared for the turbine rundown test.

00:00–01:23: unstable low-power operation

The delayed shutdown continues into the night shift. A sharp power drop, xenon poisoning, control-rod withdrawal, high coolant flow and low operating reactivity margin leave the RBMK in a difficult operating state.

00:05
Power around 720 MWt

Reactor power has fallen to about 720 MW thermal and continues decreasing.

00:28
Unexpected power collapse

During transfer between regulating systems, reactor power falls rapidly to roughly 30 MW thermal. Later reassessment did not establish a simple operator-error explanation.

00:43:27
Turbogenerator trip signal blocked

The trip signal is blocked in accordance with the test and operating arrangements. INSAG-7 later corrected the timing given in the earlier account.

01:00
Power recovered to about 200 MWt

The reactor stabilises near 200 MW thermal. Later calculations show the operating reactivity margin was below the required minimum.

01:03
Additional left-side circulation pump started

A standby main circulation pump is added on the left cooling circuit as part of test preparation.

01:07
Additional right-side circulation pump started

A further pump is started on the right circuit. Higher coolant flow changes reactor conditions and complicates steam-drum level control.

≈01:19
Feedwater increased

Operators raise feedwater flow to restore steam-drum level. Pressure and level regulation remain difficult.

01:22:30
Operating reactivity margin later calculated at eight rods

Post-accident calculations put the ORM at eight manual control rods, below the required minimum of 15.

≈01:23
Test preparations considered complete

The shift supervisors consider the unit ready and the oscilloscope used for the test is switched on.

01:23:04–about 01:24

The turbine coast-down lasts only seconds before the reactor enters a destructive transient. INSAG-7 substantially revised the earlier 1986 interpretation and placed more emphasis on RBMK design characteristics and control-rod behaviour.

01:23:04
Turbine rundown test starts

The turbine stop valves close. Four main circulation pumps supplied by the coasting turbine begin to run down. Recorded parameters initially remain within the expected range for the test conditions.

01:23:40
AZ-5 emergency shutdown pressed

The emergency shutdown button is pressed and control rods begin entering the core. The reason AZ-5 was pressed has not been definitively established.

01:23:43
Power excursion signals

Emergency signals indicate a rapid rise in power; power exceeds 530 MW thermal and continues increasing.

01:23:46
First pump pair disconnects

The first pair of rundown main circulation pumps disconnects, followed immediately by the second pair.

01:23:47
Flow and pressure change sharply

Main circulation pump flow readings and steam-separator drum pressure and water level change rapidly.

01:23:48
Fast steam-dump systems trigger

Flow partially recovers in some pumps while pressure and drum levels continue rising.

01:23:49
Fuel-channel rupture / power-loss signals

Signals indicate increased pressure in the reactor space and loss of 48-volt power to control-rod drive mechanisms.

≈01:24
Severe shocks and explosions

The operating log records severe shocks and control rods stopping before full insertion. The reactor structure is destroyed and the core is exposed.

01:28 through the rest of 26 April

The response becomes a combined plant, firefighting, medical, military, scientific and government operation.

01:28
First firefighters arrive

The first group of firefighters reaches the accident scene and begins attacking fires around Unit 4 and adjacent structures.

02:10
Unit 3 roof fire localised

Firefighters localise the roof fire on Unit 3, helping prevent spread into the neighbouring unit.

02:20
Unit 4 roof fire localised

The principal roof fire on Unit 4 is brought under local control.

≈04:00
Large firefighting force assembled

Reinforcements have brought roughly 250 firefighters to the site; dozens are directly involved in fire-control work.

≈04:00
Senior technical management expands

World History Database records place Nikolai Fomin learning of the accident at about four in the morning and travelling to the plant. Viktor Bryukhanov is already involved in plant emergency management.

05:00
Major fires reported extinguished

The principal fires are reported quenched, although the destroyed reactor continues releasing radioactive material.

Morning
Cooling and damage assessment continue

Plant personnel continue water-injection attempts, dosimetry, rescue and inspection work. Anatoly Sitnikov reports catastrophic reactor destruction.

Morning
Military and aviation response develops

World History Database records include Vladimir Pikalov conducting radiological reconnaissance and Nikolai Antoshkin organising helicopter support.

Afternoon
Government Commission and scientists arrive

Boris Shcherbina and Valery Legasov reach the Chernobyl area. The commission begins coordinating reactor assessment, radiation monitoring and emergency measures.

Afternoon
Aerial documentation begins

Photojournalist Igor Kostin records some of the earliest aerial images of the destroyed Unit 4; radiation damages much of the exposed film.

Evening
The accident is a national emergency

Plant, government, military, medical and scientific organisations are working simultaneously. Pripyat has not yet been evacuated; full evacuation begins on 27 April.

What is established, and what remains disputed

The broad sequence is well established. The shutdown delay, low-power condition, turbine test, AZ-5 action, rapid power excursion and reactor destruction are supported by instrument records and later reconstruction. The exact reason AZ-5 was pressed has not been established, and later analyses revised important elements of the first official explanation.

Control room, plant management and first response

The replacement World History Database dataset contains static records for Anatoly Dyatlov, Alexander Akimov, Leonid Toptunov, Yuri Tregub, Boris Stolyarchuk, Viktor Bryukhanov, Nikolai Fomin, Valery Legasov, Boris Shcherbina, firefighters, dosimetrists, engineers and cleanup personnel.

Chronology references

IAEA INSAG-7

The Chernobyl Accident: Updating of INSAG-1, the principal later technical reassessment.

Chornobyl Nuclear Power Plant

Accident and its Elimination.

World History Database replacement dataset

Used for named-person response records where the supplied archive supports them.

Editorial review. Compiled and edited by World History Database. Historical chronology and source links last reviewed 27 September 2026. Technical accident claims are distinguished from World History Database record material in the provenance section below.
Provenance. Exact reactor-operation times are supplementary editorial material based on INSAG-7 and the linked technical chronologies. Named-person events and descriptions are selected from the replacement Chernobyl dataset. Where that dataset gives a date but not a clock time, this page does not invent one.

Continue exploring